Brand Name : HORIZON
Model Number : Steel prop 20-350
Certification : SGS
Place of Origin : CHINA
MOQ : 2000 pcs
Price : pls ask HORIZON
Payment Terms : L/C, T/T
Supply Ability : 20000 pcs per week
Delivery Time : 15-25 days
Packaging Details : pallets, bundles, bulk
Material : Q235 steel pipe
OEM : Available
finishing : Electric galvanized
Standard : EN1065
Size : prop 20-350
Application : for supporting slab formwork
Load capacity : 20KN at top height
Typical Steel Prop 20-350 for Table Form and Flex-H20 Slab Formwork Shoring
The high load capability makes HORIZON props the top choice offering reliability and safety for any construction job.
Excellent quality is guaranteed by using high quality of raw materials, the manufacturing process and final treatment applied to the props, which result in safe and efficient use on sites.
The manufacture of Telescopic Props is certified in accordance with standard EN 1065.
Specification | Capacity (KN) | Height (mm) | Dia (mm) | Weight (Kg) |
HZP30-300 | 30 | 1650-3000 | 76/63 | 20.9 |
HZP30-350 | 30 | 1970-3500 | 76/63 | 23.0 |
HZP30-400 | 30 | 2210-4000 | 76/63 | 25.0 |
HZP20-300 | 20 | 1650-3000 | 60/48 | 15.7 |
HZP20-350 | 20 | 1970-3500 | 60/48 | 16.6 |
HZP20-450 | 20 | 2460-4500 | 60/48 | 28.2 |
HZP20-500 | 20 | 2710-5000 | 60/48 | 30.5 |
Important Instructions:
• Respect the prop spacing in accordance with the project.
• The load acting on the prop is vertical and centred. No horizontal loads act on the prop.
• Check formwork and prop erection before concrete pouring.
• Pouring has to be done from heights which do not cause strong shaking of the formwork or the props.
• Avoid the sudden emptying of the concrete bucket onto the formwork.
• Formwork stripping and prop removal is only carried out when the concrete strength is sufficiently high.
• Before starting any dismantling operation, check the state of the props.
![]() |